Fresh Start Waste has secured planning approval to double the annual capacity of its materials recovery facility (MRF) in Swinton, with the expansion allowing the site to handle up to 150,000 tonnes of waste a year.
Salford City Council’s Planning and Transportation Regulatory Panel voted eight to four in favour of the proposals on 19 November, paving the way for additional buildings and changes to the layout of the Hilton Square facility.
The application seeks to increase the site’s permitted annual throughput from 75,000 to 150,000 tonnes, alongside the construction of a new building and changes to existing waste storage and processing arrangements.
A central part of the proposals is to bring more waste handling indoors, particularly food and construction waste, as the company seeks to increase capacity and improve the management of materials at the site.
Waste processing
The facility, located at Units 4 and 5, Hilton Square, off Bolton Road operates as a commercial MRF, receiving mixed waste and recyclables before separating and preparing materials for onward recycling and recovery.
Incoming loads include dry mixed recycling, food waste, glass, wood, metals and construction materials. Waste is inspected on arrival before being directed to the relevant processing or storage areas.
At the MRF, mixed waste is sorted using a combination of manual and mechanical processes. Materials travel along conveyor belts, where workers remove recyclable items, while magnets are used to separate ferrous metals.
Paper, cardboard and plastics are recovered and prepared for onward processing, with materials such as cardboard and plastic compressed into bales. Fresh Start also describes a second sorting pass to maximise the recovery of recyclable materials.
Combustible residual waste can be shredded to produce refuse-derived fuel (RDF), which is transported elsewhere for energy recovery.
The company’s annual performance report recorded 69,355 tonnes of waste received during 2024/25, close to the existing 75,000-tonne annual permitted limit.
During that period, the report recorded 14,496 tonnes sent off-site for recycling and 20,418 tonnes for energy recovery.
New infrastructure
The expansion is intended to provide additional space for the facility’s waste handling and storage activities, with a particular focus on bringing more operations indoors.
Food waste can create odour and attract pests if it is not stored and handled appropriately. The company’s environmental documentation sets out measures including enclosed storage, sealed containers and controls over how long materials remain on site.
Construction waste will also be accommodated within the expanded arrangements.
The proposed increase to 150,000 tonnes would double the site’s existing permitted throughput, although this represents the maximum annual capacity being sought rather than a guarantee that the facility will process that volume.
Fresh Start has previously outlined a wider investment programme to increase its processing capacity, including the purchase of an adjoining building. The company has referred to a further £1.5m investment in its longer-term processing strategy, although this has not been confirmed as the cost of the latest approved works.
A separate construction cost and completion timetable for the specific expansion have not been confirmed.
Local concerns
The decision follows objections from residents living close to the Hilton Square facility, particularly on Heron Street.
It has been reported locally that residents have raised concerns about persistent smells, rats, seagulls and noise from the operation. Complaints have also focused on a bird-scarer cannon which residents say operates regularly and causes disturbance.
Some residents fear that increasing the amount of waste handled at the site could make existing problems worse.
Fresh Start has disputed claims that its operation is responsible for pest problems and has said complaints are taken seriously and investigated.
The planning committee approved the application by eight votes to four.