Recycling & Circular Economy Hub

Industry news like it should be

Menu
  • Home
  • News
  • Recycling guides
    • Can you recycle bubble wrap?
    • Can you recycle coat hangers?
    • Can you recycle Christmas cards?
    • Can you recycle light bulbs?
    • Can you recycle polystyrene?
    • Can I recycle vapes?
    • Is ‘soft plastic’ recycling a con?
    • Where can I recycle batteries?
  • Data
    • English local authority league tables
    • Northern Irish local authority league table
    • Scottish local authority league tables
    • Welsh local authority league tables
    • PRN data and market insight
    • UK incinerator map
  • About
    • Contact
Menu

Waste permit variations take an average of 260 days for EA to determine

Posted on November 18, 2026

The Environment Agency took a median of 260 days to determine applications to vary waste and recycling permits, according to figures released by the Government.

The figure was disclosed in a parliamentary written answer by Defra minister Emma Hardy on 17 November, following a question from Camborne and Redruth MP Perran Moon.

A total of 131 applications to vary waste and recycling permits were determined between 1 January 2025 and 10 November 2026.

The Environment Agency said the 260-day median includes time spent requesting and waiting for further information from applicants.

Permit variations are required when operators seek to change the conditions of an existing environmental permit. This can include proposals to increase waste processing capacity, introduce new waste streams or alter treatment processes at a facility.

The figures provide an indication of the time operators may face when seeking approval for changes to existing waste and recycling operations.

However, the Government has also highlighted improvements in the Environment Agency’s wider permitting performance.

In October, the agency said its permitting backlog had fallen by more than three-quarters, with queue times at a three-year low.

It also reported that it was processing 83% of all permitting applications on time, although this figure covers applications across its wider permitting work rather than specifically waste and recycling permit variations.

The Environment Agency has set a target of determining 95% of permits on time by March 2029.

Analysis

The 260-day figure raises questions about the time and cost involved in expanding existing waste and recycling facilities.

Operators seeking to increase processing capacity or introduce new treatment technologies may face delays before they can put planned changes into operation.

Those delays can have financial implications, particularly where businesses have already committed investment to equipment, infrastructure or additional site capacity.

However, the figure should be treated with some caution. It includes time spent waiting for applicants to provide additional information, meaning the full 260 days cannot be attributed to the Environment Agency’s own processing time.

The next question is whether determination times are improving specifically for waste and recycling operators, and how many applications are taking considerably longer than the median.

Share this:

  • Share on X (Opens in new window) X
  • Share on Facebook (Opens in new window) Facebook

Like this:

Like Loading…

Related

Leave a Reply Cancel reply

Newsletter

Popular Posts

  • November 18, 2026 Waste permit variations take an average of 260 days for EA to determine
  • November 18, 2026 Oldham considers free bulky waste collections to houses on Council Tax Support
  • November 17, 2026 Global Ardour opens at former Sims site in Aldershot
  • November 17, 2026 South Kesteven eyes  £140,000 of EPR funds to tackle driver shortages
  • November 17, 2026 East Sussex councils warned of Biffa contract overspend as fuel costs rise

About Me

With over a decade of experience in the sector, I'm looking to provide genuinely exclusive insight and helpful information all in one place.

Recent Posts

  • November 18, 2026 by Editorial team Waste permit variations take an average of 260 days for EA to determine
  • November 18, 2026 by Editorial team Oldham considers free bulky waste collections to houses on Council Tax Support
  • November 17, 2026 by Editorial team Global Ardour opens at former Sims site in Aldershot
  • November 17, 2026 by Editorial team South Kesteven eyes  £140,000 of EPR funds to tackle driver shortages
  • November 17, 2026 by Editorial team East Sussex councils warned of Biffa contract overspend as fuel costs rise

Newsletter

Sign up to our newsletter to receive an industry briefing every Thursday.

©2026 Recycling & Circular Economy Hub | Theme by SuperbThemes
%d